Create and maintain a contingency plan that identifies essential mission and business functions and associated contingency requirements.
Review contingency plans.
For high availability applications, verify the contingency plan exists and provides for the smooth transfer of all mission or business essential functions to an alternate site for the duration of an event with little or no loss of operational continuity.
For moderate availability applications, verify the contingency plan exists and provides for the resumption of mission or business essential functions within 12 hours activation or as defined in the contingency plan.
For low availability applications, verify the contingency plan exists and provides for the partial resumption of mission or business essential functions within 5 to 30 days of activation as defined in the contingency plan.
If the contingency plan does not exist or does not meet the severity level requirements, this is a finding.
V-222636
False
APSC-DV-003050
Review contingency plans.
For high availability applications, verify the contingency plan exists and provides for the smooth transfer of all mission or business essential functions to an alternate site for the duration of an event with little or no loss of operational continuity.
For moderate availability applications, verify the contingency plan exists and provides for the resumption of mission or business essential functions within 12 hours activation or as defined in the contingency plan.
For low availability applications, verify the contingency plan exists and provides for the partial resumption of mission or business essential functions within 5 to 30 days of activation as defined in the contingency plan.
If the contingency plan does not exist or does not meet the severity level requirements, this is a finding.